ECONOMY-TRANSPORT: MANILA- World Bank cancels loans for Metro Manila BRT project

.A blue rapid bus moving on the road in the city in early morning. (Photo: Getty Images). World bank

 A blue rapid bus moving on the road in the city in early morning. The World Bank had agreed with the Philippine government to cancel balance loan for the Metro Manila BRT Line 1 project. (Photo: Getty Images)
.
.
.

Three years after agreeing to disburse the monies, the World Bank has cancelled a $64 million (P3.5 billion) loan for the Metro Manila Bus Rapid Transit (BRT) Line 1 project.

According to local media reports, the World Bank noted that with less than six months left before the project’s closing date and given the lack of implementation progress, “an extension cannot be justified.”

The closing date of the Loans Agreements is November 30, 2022. The Department of Finance sent a formal cancellation request for the loan last Tuesday.

<>

Ad by:

Memento Maxima Digital Marketing
@[email protected]
SPACE RESERVE FOR ADVERTISEMENT

.

Loan granted in 2019

The loan was first approved on March 16, 2017, but the Philippines government was only able to sign off on the loans on February 14, 2019, before they were declared effective on March 15.

However, cumulative disbursement remains zero for both the $40.7 million International Bank for Reconstruction and Development (IBRD) and $23.9 million Clean Technology Fund (CTF) loans.

Only about $100,000 has been paid out of the IBRD loan for front-end fees.

While noting “renewed commitment from government counterparts”, the World Bank pointed to, among others, the “weak capacity of the implementing agency”. It noted that the National BRT Program Management Office (NPMO) reportedly had “very limited experience with BRT projects.”

The NPMO was also understaffed with a high staff turnover rate. For example, the Department of Transportation (DOT) appointed five NPMO managers and three undersecretaries to take charge of the BRT portfolio within the last three years.

<>

Ad by:

Memento Maxima Digital Marketing
@[email protected]
SPACE RESERVE FOR ADVERTISEMENT

.

Other factors included the inefficiency of procurement management, the lack of general government budget allocation and the pandemic.

·Senior Editor
·2 min read
.

Our goal is to create a safe and engaging place for users to connect over interests and passions. In order to improve our community experience, we are temporarily suspending article commenting

Ads by:
Memento Maxima Digital Marketing
@[email protected]
SPACE RESERVE FOR ADVERTISEMENT

It's only fair to share...Share on FacebookShare on Google+Tweet about this on TwitterEmail this to someonePrint this page